2021 Buchner Park Tennis Courts and Retaining Wall Reconstruction Project Update

Project Update: Sept. 17, 2021

As funded in the City’s 2021 CIP, the tennis courts and adjacent retaining wall within Buchner Park will be reconstructed in the late summer/fall of 2021.  Project work has started within the site, and will continue through October 2021.

 

Work Completed/Continued This week (9/13 – 9/17)

  • Retaining wall completed this week
  • Seed and erosion mat restoration completed behind the retaining wall
  • Removal of the remaining fencing around the tennis courts
  • Temporary fencing placed all around the project
  • Remaining old large diameter light bases removed

 

Planned Work Next Week (9/20 – 9/24)

  • Pulverizing the existing tennis court pavement 
  • Grading and removals for the new tennis court asphalt pavement

 

Traffic Control/Access

  • The Tennis courts are closed to all users.
  • The sidewalk along N. Greenfield Ave. adjacent to the retaining wall is closed.

 

If you have any questions or concerns please feel free to contact me. 

 



Brandon Schwenn, P.E.

Project Engineer

City of Waukesha – Engineering Division

Phone: 262-524-3585

Email: bschwenn@waukesha-wi.gov 