Drop Off Center Retaining Wall Construction

Project Update: September 17, 2021


The contractor finished pouring all the walls and the backfilling is complete.  The surface pavement will begin next week.  The estimated completion is Sept 30, 2021.

The site will be open on the normal hours.  Beginning next week there will be multiple large dumpsters for trash and the the area for brush and branches will be open.

If you have any questions please contact the project manager below.


Katie Jelacic, P.E.
Project Engineer
kjelacic@waukesha-wi.gov
262-349-6511 (c)
262-524-3587 (o)


Sept 17 Update