Project Update: August 24, 2020 (Final Project Update)
This Project includes the following work:
- Installing new underground conduit and wiring
- Installing a new concrete light pole bases
- Installing a new LED decorative light poles and luminaries.
Work Completed this week
- Final Pole and Luminaire installation.
Anticipated work next week
Future work