Sanitary Sewer Manhole Rehabilitation, 2020
Construction Update: August 28, 2020 (Final Update)
This project involved rehabilitating sanitary sewer manholes along sections of:
- Tall Grass Cir
- Tree Line Ct
- Highfield Rd
- Hunter Rd
- Deer Path
- Hunter Ct
- Other selected areas around the City
This week’s work:
- Completed work on remaining manholes. All work is complete on the project.
Next week’s work:
Streets with restricted access for the next week:
Streets that will have No Access for the next week:
This will represent the last project update as all work has been completed. The City would like to thank the residents for their patience and cooperation throughout this project.
Please contact the Project Manager with any questions (information below)
Jonathan Schapekahm, P.E.
Project Engineer / CMOM Coordinator
City of Waukesha
P:262-524-3584
jschapekahm@waukesha-wi.gov
www.waukesha-wi.gov