Project Update: October 26, 2020

Frame Park:

 

As soon as the dugouts are installed this week Thursday, the project will be ready to have its final inspection from the consultant, the City and Carroll University.  

 

Mindiola Park:

 

This week the contractor will continue their work on the concrete curb that goes around the field.  The Light bases were all drilled and the foundation of the lights are being installed.


The project consists of the following:

Frame Park Baseball:

  • Installation of Synthetic Turf for infield and outfield of Ball Diamond
  • Reconstruction of Dugouts and Fencing

Mindiola Park Soccer Field

  • Approximately 95,000 Sq. Ft Synthetic Turf Installation
  • Back Up Net System and Fencing
  • Field Lightening

If you have any concerns or questions please contact the Project Manager Below:


Katie Jelacic, P.E.
Project Engineer
262-524-3587 (o)
262-349-6511 (c)