Roberta & Tenny Ave. Utility & Street Improvements

Project Update: May 29, 2020

This week the contractor completed the water main installation along both Roberta Ave. and Tenny Ave. and have now started the water service installations to properties along Roberta Avenue. The contractor also completed a sanitary sewer spot repair and installed more sanitary lateral cleanouts around the project in preparation for the sanitary lateral lining. Next week the property water service installations will continue as the crew works along Roberta Avenue and will then continue along Tenny Avenue once the services on Roberta Ave. are complete. Late in the week, they may begin sawcutting the existing pavement in preparation for the removal of the existing roadway once all of the water main work has completed.

Traffic Control/Access

Roberta Avenue is closed to through traffic from East Avenue to Tenny Avenue, and Roberta Avenue is closed to through traffic from Oakwood Drive to Tenny Avenue (Including the Roberta/Tenny intersection). Access to residential driveways within the closure limits (local traffic) will be allowed into the work zone.

All the dates and times above are subject to change and are weather dependent. I will update the group if anything changes from the above information. If you have any questions or concerns regarding the project, please feel free to contact me.

Project Manager
Brandon Schwenn, P.E.
Project Engineer
City of Waukesha – Engineering Division
(262) 524-3585
bschwenn@waukesha-wi.gov
www.waukesha-wi.gov