Greenmeadow Sanitary Interceptor Sewer

Project Update: May 22, 2020 (Last Project Update)

This project included installation of a new sanitary interceptor sewer from the intersection of Greenmeadow Dr. and Michigan Ave. to the intersection of College Ave. and Sentry Dr. This sewer has allowed the elimination of the Greenmeadow and Woodfield pump stations.

This week’s work:

  • Restoration sod/seed work on project
  • Installed pavement striping on project

Next week’s work:

  • Seed old pump station site at Greenmeadow & Michigan
  • Wrap up any loose ends of project and finalize all work
  • City will walk through the project to confirm all work has been completed satisfactorily. Any items identified will be addressed and the project will then be closed out.

Streets with restricted access for the next week:

  • None

Streets that will have No Access for the next week:

  • None

All restoration work remaining on the project (final asphalt, sod, striping, etc) is scheduled to be completed near the end of May.

Please contact the Project Engineer with any questions.


Project Engineer Contact Information:
Jonathan Schapekahm, P.E.
Project Engineer / CMOM Coordinator
City of Waukesha
P:262-524-3584
jschapekahm@waukesha-wi.gov
www.waukesha-wi.gov