Sanitary Sewer Lining- Pebble Valley Area

Project Update: December 7, 2020 (FINAL UPDATE)

 

This project includes the following work:

  • Repairing manholes as necessary (completed)
  • Cleaning, inspecting and installing a liner in the main line sewers (completed)
  • Installing a cleanout on the individual laterals, cleaning, inspecting and lining the laterals in the right-of-way (completed)
  • Restorations as necessary (completed)

 

Previous work:

  • The contactor completed the restorations.

 

Future work:

  • The contractor will be addressing any punch list items.

 

Streets with restricted access for the this week:

  • None

 

Streets that will have No Access:

  • None

Please feel free to call or email with any questions or concerns.