Project Update November 16, 2018 (Final Update)

The demolition and backfilling is complete. The contractor is trying to schedule the seed and mulch for this week, but may have to be scheduled for more seasonal weather.

The demolition of the Gas Station Property adjacent to the site will be scheduled for early in 2019.

The City of Waukesha purchased the strip mall in March 2018.  The City received a grant from the WEDC to assist in the asbestos abatement and demolition of the building in the fall of 2018.  The City is working with developers on a redevelopment plans to assist in determining the highest best use of the property and to redevelop the property into a tax generating commercial/mixed use development.

If you have any questions please contact me.