Dunbar/Bethesda/Prospect Reconstruction

Project Update March 15, 2019

This week the City’s contractor finished installing the new sanitary main in Bethesda Park and along Bethesda Court. They also began replacing some of the sanitary laterals, and began the new watermain on Dunbar Avenue.

Next week the City’s contractor will continue to work on the sanitary laterals and the new watermain on Dunbar Avenue.

Dunbar Avenue (Marshall St to N. West Avenue), Bethesda Court (Dunbar Avenue to Prospect Court) and Prospect Court (Bethesda Court to N. West Avenue) will be closed to through traffic (local traffic only). Access to resident’s properties will be maintained until the contractor paves the road.

Any questions regarding this project please contact me at your earliest convenience.

Thank you,

Craig Ausen, P.E.
Project Engineer
City of Waukesha – Engineering Division