Project Update July 12, 2019

This week the City’s contractor continued pouring sidewalk and drive approaches throughout the project. They also continued grading the terrace to match the new curb and gutter and installed the new street lights. Please remain off the new drive approach and sidewalk with vehicles if the contractor has placed barrels in front of your drive approach, moving the barrels to drive into your driveway may void the warranty on the concrete.

Next week the contractor plans on finishing all remaining concrete, and begin the restoration on the project.

Any questions regarding this project please contact me at your earliest convenience.