Water Utility's E. Main St. Utility and Street Reconstruction Project

Project Update: October 12, 2018

Main Street reconstruction continued this week with grading work and preparation for additional concrete pavement to be installed next week. All underground utility work has been completed, with the exception of some electrical work for street lights and the traffic signal at East Avenue.

On Monday and Tuesday, Zignego plans to pour curb and gutter adjacent to the recently installed west bound lane. Then on Wednesday 10/17, the east bound mainline lane is scheduled to be poured the entire project limits from Barstow to Lombardi. We continue to work closely with local businesses to accommodate access and minimize the time frames they are impacted while the concrete is being installed.

Sidewalks and driveways are scheduled to be completed during the last week of October and first week of November. Final electrical work for new signals and street lighting will also be completed during that time. Pavement marking and lawn restoration should be completed the second week of November.

Temporary thru-access closures on cross streets will occur during paving operations and we ask for your continued cooperation and patience. Businesses and residents will receive a minimum of 24-hour notice prior to driveway paving or other times under which direct access to their property is restricted. Please contact me with any questions.

Click Here for Detour

Chris J. Walter, P.E.
Technical Services Manager
Waukesha Water Utility | P. O. Box 1648 | Waukesha, Wisconsin 53187-1648 | (262) 521-5272
(262) 409-4460 | (262) 901-5886 | * cwalter@waukesha-water.com | www.waukesha-water.com

IMG_4527
Main Street EXHIBIT