Water Utility's E. Main St. Utility and Street Reconstruction Project

Project Update: Oct. 18 , 2019

This week the City’s contractor is completing the pavement at the intersection of Main St/Perkins Ave/Cleveland Ave, the curb and gutter from Lombardi Way to Perkins Avenue, curb and gutter on Aurora Street. They also began installing drive approaches between Lombardi Way and Perkins Avenue.

Next week the contractor plans on paving concrete on Aurora St, continue pouring curb and gutter from Perkins Avenue to Manhattan Dr, pouring sidewalk and drive approaches, and begin sealing and installing the pavement markings.

During this time Main St remains closed (local traffic only).

Any questions regarding this project, please contact me at your earliest convenience.

Chris J. Walter, P.E.
Technical Services Manager
Waukesha Water Utility | P. O. Box 1648 | Waukesha, Wisconsin 53187-1648 | (262) 521-5272
(262) 409-4460 | (262) 901-5886 | * cwalter@waukesha-water.com | www.waukesha-water.com

Main St.