Northview Rd Utility and Street Reconstruction Phase II

Project Update Aug 9, 2019

Just an update on the remaining work along Northview Rd., and within Meadowview Park. The contractor still has the final restoration work remaining along Northview Rd. and will have a crew completing the work early next week. They will be touching up any areas of topsoil and prepping the areas for seeding or sod placement. Since this work will be completed under live traffic, there will be traffic control devices along the project protecting the direct work area. Please use caution while traveling along the project area next week.

Within Meadowview Park, the grading work is almost complete around the park, just a few spot areas remain. The contractor will be paving the pathway system in the near future, and after the paving work is complete, final restoration will be completed in the remaining areas of the park site.

After the work along Northview wraps up, the contractor will be completing any remaining cleanup/punch list type activities around the project limits. We are aware of cracks that have occurred in the new areas of sidewalk along the project, and they will be replaced by the contractor as a punch list/project closeout activity.

All of the dates and times are subject to change and are weather dependent. I will update the group if any work activities described above change. Thank you for your cooperation during this reconstruction project, and if you have any questions or concerns please feel free to contact me.

Phase 2 Overview

Phase 2 Detour

Phase 2 Public Information Handout

As many of you are aware, the City of Waukesha will be reconstructing Northview Rd. from Meadowbrook Rd. (STH 318) to Tallgrass Cir. in the spring/early summer of 2019. This will be the second phase of work along Northview Rd. and a continuation of the Phase 1 project that reconstructed Northview Rd. from Tallgrass Cir. to N. Grandview Blvd. in 2018. This proposed improvements of the Phase 2 project include the complete reconstruction of the roadway, installation of storm sewer improvements, minor sanitary sewer and water main/hydrant adjustment work, installation of new permanent signing and pavement markings, sidewalk will be constructed in portions of the project corridor; and grading for the future placement of sidewalk will be performed elsewhere. This project also includes the Phase 1 improvements of the Meadowview Park site at the corner of Meadowbrook Rd. and Northview Rd.

During the project work, Northview Rd. will be closed to through traffic from Meadowbrook Rd. to Tallgrass Cir., and a proposed detour route (Meadowbrook Rd. -> Silvernail Rd. -> N. Grandview Blvd.) will also be posted. The contractor for this project, has tentatively scheduled a starting date of Wednesday March 27th for the project, and as a result, beginning on 3/27, Northview Rd. from Meadowbrook Rd. to Tallgrass Cir. will be closed to through traffic.

If you have any questions or concerns with the upcoming project, or project start time please feel free to contact me.

If you would like to sign up for weekly, or sometimes more frequent, email updates during construction, please send your email address to Brandon Schwenn, bschwenn@waukesha-wi.gov


Project Contact Information:

Brandon Schwenn
Project Engineer
City of Waukesha
130 Delafield Street
Waukesha, WI 53188-3646
262-524-3585

bschwenn@waukesha-wi.gov